* The Conditions Impacting Transmission Capability page
is manually updated once per day to include transmission outages within the
Special Notices: Transmission Service
BGE is revising transmission
circuit and transformer ratings in their transmission zone based on a
comprehensive review of their facility ratings process.
PJM is reviewing the 500 and
230kV transmission circuit and transformer ratings which will be implemented on
The BGE rating changes
effective June 1 are included in the attached document:
Emergency and Planned
Outages are scheduled on the following 9 facilities during May to address
projected operational/reliability concerns.
|
Circuit No |
Location |
eDART Ticket Numbers |
Outage Dates |
|
2314 |
HIGH RIDGE
TO |
276710 |
|
|
|
|
|
1 daily
outage |
|
2334 |
HIGH RIDGE
TO |
276712 |
|
|
|
|
|
1 daily
outage |
|
2344 |
|
226517 |
|
|
|
SOLLERS
POINT TO |
|
3 daily
outages |
|
|
|
276755 |
|
|
|
|
|
2
daily outages |
|
2345 |
|
276774 |
|
|
|
SOLLERS
POINT TO |
276788 |
|
|
|
|
276789 |
|
|
|
|
|
3
daily outages |
|
2310 |
CONASTONE
TO NORTHWEST |
231410 |
5/16/2008-5/18/2008 |
|
|
|
|
3 daily
outages |
|
|
|
|
|
|
2322 |
CONASTONE
TO NORTHWEST |
276734 |
|
|
|
|
|
1 daily
outage |
|
2323 |
CONASTONE
TO GRACETON |
276753 |
|
|
|
|
|
1 daily
outage |
|
2313 |
GRACETON
TO |
276749 |
5/12/2008-5/14/2008 |
|
|
|
|
3 daily
outages |
|
|
GRACETON
230-1 |
276754 |
|
|
|
|
|
1 daily
outage |
BGE is in the process of performing a comprehensive review of their 115kV facility rating. Results will be communicated via OASIS upon completion of the review.
http://www.pjm.com/etools/oasis/downloads/20080501-bge-ratings-changes-for-june-1-2008.xls
Update
Due to issues with the eMKT database, Mt. Storm – Pruntytown 500 kV line outage has been delayed from its original timeframe - April 15 thru 17, 2008 to April 16 thru 18, 2008 in order to ensure that the potential congestion during this outage is appropriately captured in the day-ahead market case.
Update
Work was completed under eDART #237768 and the
Update
Due to a revised work plan, FE East has submitted eDart
ticket #237768 scheduled for 2/25-2/29. This outage replaces eDart ticket #230048, which has now been
‘cancelled’. Upon completion of eDart
#237768, the
Update 2/11/08
Upon completion of eDart ticket #230048, the ratings
of the East Towanda #3 230/115kV transformer will increase ~50% for all
temperature sets. However, an additional transmission outage will be required
to return the Transformer to its pre-July 2007 ratings. This second outage has
not yet been scheduled.
Update 1/15/07
On Thursday 1/10/07, the Operating Committee waived the 90-Day waiting
period defined in
In early July of 2007, FE East discovered the
Black Oak SVC
Update –
The new Black Oak Static
WYLIE RIDGE STATION
Update –
The Wylie Ridge #6 345/500kV transformer is expected to be in-service on
Wylie Ridge #8 345/500kV transformer was placed in-service
on
**No
longer applicable**
A
Special Protection Scheme has been installed at the Wylie Ridge station in
order to reduce the post-contingency flow on the Wylie Ridge 500/345 kV
transformers and reduce congestion at this station. Upon the loss of a Wylie
Ridge 500/345 kV transformer, the SPS trips the ‘WK1’ and the
‘WK6’ 345 kV circuit breaker to split the 345 kV bus so that the
remaining Wylie Ridge 500/345 kV transformer is isolated on the Wylie
Ridge-Tidd 345 kV line.
KAMMER 765/500kV TRANSFORMER DERATE
On
Update –
On
ALLEGHENY POWER EHV TRANSFORMERS
Update –
This update provides additional information regarding the de-rating of the Wylie Ridge #7 EHV transformer. The Wylie Ridge #7 transformer was de-rated by approximate 13%. At this time, there are no plans to de-rate the parallel transformer (Wylie Ridge #5). The decrease in rating will impact congestion in the Wylie Ridge area and transmission service on those paths that are limited by constraints at Wylie Ridge.
Update –
Allegheny Power has completed a portion of it’s
analysis on several of their EHV transformers, located at Wylie Ridge,
WYLIE RIDGE,
As a result of the recent review of transformer performance parameters, the New Freedom 500-4 500/230 kV transformer has been de-rated by approximately 15%. No significant increase in congestion and off-cost operation is expected due to the decrease of transformation capability at New Freedom.
Hunterstown #1 500/230 kV transformer
Out
of service January 21 thru
Marquis – DOE #2 345 kV line
Out
of service
Marysville – Maliszewski 765 kV line
Out
of service March 3 thru
Kammer – Maliszewski 765 kV line
Maliszewski 765/138 kV transformer
Out
of service March 3 thru
Ox #2 500/230 kV transformer
Out
of service March 3 thru
Hanging Rock –
Out
of service March 3 thru
Out
of service March 29 thru
Baker – Hanging Rock 765 kV line
Out
of service March 31 thru
Out of service
March 31 thru
Greene – Sugar Creek 345 kV line
Out of service April 18 thru 30, 2008
Bedington – Black Oak 500 kV line
Black Oak – Hatfield 500 kV line
Out
of service April 26 thru
Surry – Chickahominy 500 kV line
Out of service
April 27 thru
Davis Creek – Braidwood 345 kV line
Out of service
April 25 thru
Burnham -
Out
of service April 28 thru
Ladysmith – Chancellor 500 kV line
Out of service April 28 thru 29, 2008
Out
of service April 28 thru
Pruntytown #1 500/138 kV transformer
Out
of service April 28 thru
Conastone – Hunterstown 500 kV line
Scheduled
out of service May 3 thru 5, 2008
Scheduled
out of service May 3 thru 16, 2008
Peach Bottom –
Scheduled
out of service May 5 thru 9, 2008
Scheduled
out of service May 5 thru 9, 2008
Hanging Rock - Marquis 765 kV line
Scheduled
out of service May 5 thru 16, 2008
Kammer – W Bellaire 345 kV line
Tidd – W Bellaire 345 kV line
Scheduled
out of service May 5 thru 8, 2008
Kammer - Maliszewski 765 kV line
Scheduled out of service May 5 thru 30, 2008
Scheduled out of service May 5 thru 8, 2008
S. Canton 765/345 kV transformer
Scheduled
out of service May 5 thru 9, 2008
Conastone 500-2 500/230 kV transformer
Scheduled
out of service May 11 thru 17, 2008
Conemaugh – Keystone 500 kV line
Scheduled
out of service May 12 thru 30, 2008
Alburtis - Branchburg 500 kV line
Scheduled
out of service May 12 thru 20, 2008
Scheduled
out of service May 13 thru 15, 2008
Scheduled out of service May 14 thru 15, 2008
Conastone 500-3 500/230 kV transformer
Scheduled
out of service May 18 thru 19, 2008
Cloverdale
–
Scheduled
out of service May 19 thru 22, 2008
Calvert Cliffs – Waugh Chapel 500 kV line
Scheduled
out of service May 21 thru 23, 2008
Alburtis
-
Scheduled
out of service
JUNE 2008 OUTAGES
Hanging Rock –
Scheduled
out of service June 2 thru 27, 2008
Scheduled
out of service June 2 thru 13, 2008
Cloverdale 765/345 kV transformer
Scheduled
out of service June 2 thru 5, 2008
Cloverdale – Joshua Falls 765 kV line
Scheduled
out of service June 9 thru 12, 2008
Tanners Creek – Miamifort 345 kV line
Scheduled
out of service June 25 thru 26, 2008